Thiruvananthapuram: Kerala State Electricity Board (KSEB) is overhauling its project implementation department to accelerate the progress of new power generation ventures. This decision comes in response to serious delays observed in completing various projects, especially in hydropower. According to a three year old report by Jacob Muthirendikal, former project manager of the Pallivasal project, all these projects together have caused a loss of over Rs 30,000 crore. 

The 40 MW Thottiyar project remains unfinished even after 17 years. Similarly, projects like the Pallivasal extension (60 MW) and the Sengulam augmentation (85 million units), initiated in 2009, have seen little progress. The Pallivasal project, which started on March 1, 2007, was expected to be completed by March 1, 2011. Items brought in for various projects were rusted and destroyed. Environmental issues hindered the 40 MW Pampar project and the 30 MW Achankovil project. The 24 MW Sengulam Augmentation Project was halted due to a technical glitch. Over the past 15 years, only 192.91 MW has been added through hydropower projects, falling short of anticipated targets and risking an impending energy crisis.

Issues such as lack of experience among project management personnel and frequent transfers have affected departmental efficiency. Engineers have also been noted to lack adequate technical training. Disjointed coordination between civil and electrical sections has further impeded project timelines, affecting critical phases like dam construction and generator installation.

To address these challenges, KSEB has appointed a chief engineer to oversee new projects categorically: hydel, wind, pumped storage, and solar. Specialised training programs will be initiated for project management roles at various levels, including Executive Engineers, Assistant Executive Engineers, and Assistant Engineers. The objective is to ensure projects are completed within stipulated timelines, safeguarding against future energy shortages.