11.5 km of tunnels, 13 km of bridges under SilverLine project, reveals DPR

Thiruvananthapuram: The details of the Detailed Project Report (DPR) of the Thiruvananthapuram – Kasaragod Semi High-Speed Rail (SilverLine) project has come out. The private company Systra has prepared the DPR for the project under Kerala Rail Development Corporation (K-Rail). The report on this was submitted to K-Rail a year ago.
The justifications listed in the DPR is that Kerala’s existing railway system is inadequate compared to its population. The project requires a total of 1222.45 hectares of land. Out of this, 1074.19 hectares of land is private property.
107.98 hectares of land owned by the government and 44.28 hectares of land owned by the Railways will be required for the SilverLine project.
190 km of the railway track will pass through villages and 88 km through fields and wetlands. 50 km track will pass through small cities and 40 km through urban and semi-urban areas. 3 km of road will pass through Kochi city and 60 km will pass through railway land.
There will be 11.5 km of tunnels and 13 km of bridges on the SilverLine track. 88.412 km of track will be above ground level and 292.728 km of track will be at ground level. The construction of tracks will require levelling of mountains and hills. The DPR also pointed out that levelling of mountains and hills will cut the expenditure.